Last year the Hungarian state paid the owners of the major Hungarian highways M5 and M6 114 billion forints (351,4 million euros). These are the most expensive concession agreements between the public and the private sector in Hungary. In the public, these are more prominently known by their English acronym, Public-Private Partnership (PPP) agreements. Liberal economists tend to regard these financial instruments as socially beneficial. They were first deployed in Hungary between 2002 and 2010 by the coalition government comprising the major center-left force in Hungarian politics at the time, the Hungarian Socialist Party (MSZP), and the left-liberal Alliance of Free Democrats (SZDSZ). PPPs were also heavily promoted by the European Union: the theory was that private corporations would be able to realize investment projects more cost-effectively and faster than the state, and that they would also provide higher quality maintenance. Hence, taxpayers would be better off. For politicians, the main benefit of PPP projects is that they can realize investments without immediately burdening the state budget.
On the whole, PPP is not an overly complex structure. Essentially, the idea is that a company performs an investment that would normally be performed by the state, and then keeps operating the resulting service for a long time, potentially several decades, while the state pays the private company back in annual installments. Although this does not increase the country’s public debt, in reality it is but an accounting trick: Eurostat may not include PPP projects in its calculations of the public debt, but they constitute a debt burden all the same, just as if the investment had been funded by issuing treasury bonds.
With respect to the projects we investigated, the first round was the construction of the section of the M5 highway between Kiskunfélegyháza and the Serbian border, which was built based on a concession extended to a joint company set up by the Austrian Bau Holding AG and the French Bouygues S.A. and Colas S.A corporations. Back then, what was later to become known as a PPP was called a concession, and this instrument was seen as more beneficial for the state: it did not need to pay for it at all, the company was allowed to collect tolls instead – the right to toll collection was set to expire after 35 years, after which time the company would have to cede the right back to the state. However, the toll was so high that hardly anyone used the highway, while there was immense traffic on the parallel Route 5, which is a freeway. That is why the decision was made in 2014 to integrate the highway into the national highway sticker system, with the state paying 17 billion forints (52,4 million euros) in return, for which it received a 40% share of the highway. The state also had an option to buy the remaining 60% for another 100 billion, but decided instead to sell its own stake at a depressed price, estimated at about 21 billion forints (64,7 million euros), to foreign owners. So in the end it was left with an annual bill in the amount of 35 billion forints (107,9 million euros) for 26 years in exchange for public access to the highway section. It does not take substantial math skills to figure out that this was an awful deal since the entire construction would have cost about as much as the state paid in three years’ worth of fees.
Another major highway, M6, was probably the worst public investment of the center-left MSZP-SZDSZ coalition government: especially south of Szekszárd, traffic tends to be very low, roughly on par with the traffic of a typical subordinated free road.
The government pushed for the project because Pécs became Europe’s cultural capital in 2010, and the assumption at the time was that this status demanded highway access even though both Tallinn and Riga had been able to function as cultural capitals without a highway access. The other mistaken assumption was that the highway would inevitably generate economic progress. Reality defied these expectations, however. The counties along the highway, Tolna and Baranya, have not experienced a boom, not a single major investment project occurred in this region, and these counties keep falling behind economically.
The government opted for the PPP solution because of the rising budget deficit and the resulting EU infringement procedure. It is worth taking a look at how the minister of the economy at the time, János Kóka, argued for this solution back in 2007. In hindsight, his reasoning is likely to elicit a bitter smile, since not even a fraction of the great expectations at the time have been met. European consulting companies specializing in drafting viability studies for all kinds of projects did so in the case of the M6 highway as well. The crown jewel of the investment project were tunnels dug into four hills, which the whole country continues to marvel at to this day.
The scope of the state’s annual financial obligation is aptly illustrated by the fact that last year it had to pay 114 billion forints (351,4 million euros) out of the 315 billion forints (971 million euros) overall which it collected from the sales of electronic highway stickers throughout Hungary just to pay for the cost of the 359-kilometer-highway section affected by the PPP contracts. In other words, 36% of the total amount raised by highway fees had to be devoted to cover the costs associated with a mere 15% of the total toll highway network. * If we further also consider the amount of traffic on the PPP sections of the toll roads, then the disproportionality becomes even more striking: based on our calculation for last year, the M6 highway has generated an annual loss of 50 billion forints (154,1 million euros).
We collected data from the budgets between 2010 and 2018 to ascertain how much the state has paid over this period for the M5 and M6 highways, and we compared the results with the total revenue from sales generated by the companies that operate the highway. Over the past nine years, the state paid a total of 941.5 billion forints (2,9 billion euros) for the maintenance and use of the PPP highways, of which 200.6 billion went straight back into the state budges as VAT. Interestingly, there are massive discrepancies between the budget data and the companies’ revenues in some years. On the whole, their revenue exceeded the total paid by the state by an amount of 12.6 billion forints (38,8 million euros); the companies may have generated additional revenue from the businesses that operate rest stops along the highways.
It is worthwhile to take a more detailed look into the financial data about the companies that operate the highways in question. One truly astonishing facet of their financial results is that their operating profit amounted to half of their total revenue over the past nine years. * Not all the companies divulged information about the amount of dividends they paid out for all of the years in question, but based on the data that we did manage to find 76.3% of the profits were paid out to the owners in the form of dividends. A significant slice of the remaining profits was probably also funneled to the owners, since there were loans that were repaid to the owners from the company’s profits. We also found that the amount of annual depreciation registered in the company’s accounting records ranged between a mere 25-35.1 billion: this is the amount whereby the value of the investment depreciates as a result of wear based on the accounting rules – the annual availability fee exceeds this by several orders of magnitude.
The State Audit Office of Hungary has reviewed the highway PPP contracts on several occasions and has criticized a variety of issues without quantifying the extent of the financial damage suffered by the Hungarian state as a consequence. We used two methods to try to gauge the extent of the damage:
- We looked at the after-tax earnings of the companies that operate the highway, and we looked at the estimated inflation-adjusted total of these earnings (we assumed an annual inflation of 3%) until the expiration of the concession contracts. When it comes to operating a highway, we find it difficult to believe – and hence to assume – that the Hungarian Public Road (Magyar Közút) company would perform this substantially worse or less effectively than the concession holders. The construction of the highways was performed by the standard companies that tend to build roads in Hungary. Moreover, these companies definitely had to pay a higher interest on the outside financing of the project than the Hungarian state. In other words, the after-tax earnings that these companies have generated would have certainly accrued to the Hungarian state if it had chosen to build and operate the given sections of the highway itself. Using this as the basis for our calculations, the losses to the state amount to 99 billion forints (305,1 million euros) thus far. Furthermore, from 2019 to the expiration of the contract – based on the trends observed thus far – the companies will profit to the tune of another 435 billion forints (1,3 billion euros). It follows, therefore, that up to the expiration of the contract, the Hungarian state is forgoing 534 billion (1,6 billion in euros) in profits because of the PPP contracts for the two highways; these profits are accruing to two foreign investors instead.
- Based on the construction costs – and in the case of M5 also on the basis of the investment* costs – we calculated how much the state would have had to spend over the entire contractual period to fund the project itself by securing a loan instead of going down the PPP path. For this estimate, we looked at the average interest rate actually paid by the Government Debt Management Agency (Államadósság Kezelő Központ) since the projects were implemented, and for the remaining period after 2019 we assumed an average interest rate of 3%. As for maintenance, we relied on the annual report of the Hungarian Public Road company, on the basis of which we estimated that the annual maintenance of a kilometer of highway costs around 11 million forints (34 000 euros);* we also adjusted this figure for annual inflation. It is important to note that this significantly overestimates the actual maintenance costs, since a third of the 11 million forints (34 000 euros) is actually depreciation. Considering all of the above, the result of our calculations is that if the highway sections had been built with loans taken out by the state, then the interest would have been equivalent to the average interest of government bonds during this time, assuming a total loan period that is equivalent to the duration of the PPP contracts, calculating with an estimated 3% inflation and interest after 2019.
This is what the difference between the loan and the PPP arrangement would have looked like for each of the years in question:
Our calculations suggest that if the state had chosen to realize the M5 and M6 projects by taking out a loan instead of opting for the PPP contracts, then it could have saved 2,853 billion forints (8,8 million euros) in total, the equivalent of 7% of Hungary’s annual GDP today. This figure falls only 93 billion (286,7 million in euros) short of the total sum of the funds in the private pension funds that the Hungarian government nationalized in 2011.
Another way of approaching this issue is to ask what would have happened if instead of paying the availability fees based on the concessions, we would have used the same money to build highways at an estimated price of 3 billion forints (9,2 million euros) per kilometer, the typical price during this period. Since the case of M5 is slightly more complicated – in that case a share acquisition in the highway was replaced by a PPP arrangement – let us focus only on the case of the M6. Using the amount of money allocated to covering the availability fees, the M6 could have been completed by 2018, and with the money owed by the state for the remaining period of the contract, a total of 900 kilometers of new highways could have been constructed by 2040! Thus, for the benefit of completing the M6 eight years earlier, the public lost out on the construction of 710 kilometers of highways.
This project – and PPPs in general – were heavily criticized by Fidesz while it was in opposition. Back then, it promised to renegotiate these contracts. With respect to the highways in question, all the government did was to commission a domestic law firm to review the contracts for a fee of 17 million forints (52 404 euros), and then: nothing.
PPP projects are characterized by a complete lack of transparency: even today we do not have access to the concession contract, which raises the suspicion that they are hotbeds of corruption.
The Ministry of Innovation and Technology has failed to respond to our questions concerning this matter, and our freedom of information requests for the concession contracts were in vain. Not only did the ministry fail to divulge the contracts in violation of the relevant legal deadlines and requirements, but it also failed to explain or justify its failure to comply with the FOI request.
The only relevant information that can be found are the notices in the public procurement bulletin about the concession contracts concerning the two sections of the M6, but the contracts themselves are missing from the public procurement database (Section 2 and Section 3). The text of the contracts might provide us with an answer to the question why the state cannot wriggle out of these awful arrangements. Construction companies that move around with ease in the complicated world of legal and international conventions try to shield themselves from such measures by relying on rules protecting international investors. To put a complicated story in simple terms: no matter how much of a whiff of corruption or potentially fraudulent profits attaches to a given project, the companies can still insist on keeping the resulting profits. If subsequent governments were to cut into these profits, the companies would certifiably win in international court and the state would also have to pay substantial damages on top of repaying the companies their lost profits.
We also contacted the companies in question to ask them whether they think that their excessively high rate of profits on these projects are fair and what their return-on-investment calculations are. Only one of those contacted, the AKA Zrt, responded to our query:
Based on the concession contract concluded in 1994, our company has assumed the responsibility for the comprehensive planning, construction, financing, operation and maintenance of the M5 highway for a period of 35 years. The concession contract does not constitute public information. The returns on this project can only be credibly calculated at the end of the contractual period.
We were not alone in our suspicions about the high rates of profits – the UN organization working on encouraging international investments, UNCTAD, has also looked at the issue: Based on research conducted by Columbia University, they wrote last year that international investment protections and PPP projects constitute a high-risk combination – Hungarians learned this lesson the hard way, wasting a lot of money in the process. Let’s take a look at who the owners of the individual PPP highway sections are:
- AKA Alföldi Koncessziós Autópálya Zrt.: Strabag (by way of the M5 Holding GmbH registered in Vienna)
- M6 Duna Autópálya Koncessziós Zrt.: Aberdeen Asset Management, EBRD, Intertoll
- M6 Tolna Autópálya Koncessziós Zrt.: Aberdeen Asset Management, EBRD, Intertoll
- Mecsek Autópálya Koncessziós Zrt.: Strabag, Colas, Bouygues, John Laing Infrastructure Limited, Intertoll
During the reign of the left-liberal MSZP-SZDSZ coalition, Strabag was seen as nurturing close ties with the liberal SZDSZ, which is why the company was a regular target of Fidesz criticisms. Nevertheless, after 2010 Strabag managed to change course, and these days they support Orbán’s soccer academy at Felcsút and Fidesz-aligned media. Their pivot was so effective that they became suspiciously cozy even with Orbán’s chief financial frontman, Lőrinc Mészáros, in the context of the Belfry company. Quietly, Strabag has emerged as the king of infrastructural construction work, edging out even companies that have traditionally close personal ties to the ruling party.
The EBRD (European Bank for Reconstruction and Development) is an international bank owned by the United States and European nations. This international institution has been involved in a wide variety of corruption affairs (see here, here, here and here). In Hungary, too, it extended a loan to the Budapest Public Transportation Center’s (BKK) ultimately failed e-ticketing system; this loan came with highly disadvantageous conditions attached, and one stipulation was that the procurement process would have to be non-transparent. The bank also had other plans in store for Hungary: they wanted to repair minor highways using PPPs, and they also sought to extend the use of these financial instruments to municipal governments.
The fact that PPP projects have been discontinued in Hungary is definitely a positive development – even at what we assume are highly inflated price tags, publicly-funded constructions cause less damage to Hungary.
This article was written by Peter Bucsky, and was first published on g7.hu, DemNet’s media partner, with the goal of presenting the problem with PPPS to the Hungarian readers and raising awareness about it in the wider public. Read our other article on how a Hungarian billionaire made superprofit on an art PPP here.